Mapara Road footpath
AUGUST 7, 2020
The first section of the new Mapara Road footpath is nearing completion, with chip seal added and street light ducting installed. The local contractor TR Construction have already commenced work on the next section progressing downhill, with new kerbing to be constructed next week and new footpath expected to be complete by the end of August 2020.
JUNE 11, 2020
Construction of a footpath and kerb and channeling on Mapara Road started this week, with the first section of concrete kerb already poured opposite Acacia Heights Road.